当前位置:网站首页>2022 supervision engineer contract management exercises and answers
2022 supervision engineer contract management exercises and answers
2022-04-21 13:32:00 【Laughing at online classes】

1、 The adjudication committee generally visits the site during key construction operations , However, the interval between the two visits shall not be less than (D) God .
A.56
B.84
C.96
D.140
2、 The following statements about the bidding agency are incorrect (B)
A. The bidding agency must obtain the qualification recognition of the competent construction administrative department
B. The bidding agency must be subordinate to the Construction Committee and other administrative organs
C. The bidding agency must have the ability to prepare bidding documents
D. The bidding agency must have technical personnel as members of the bid evaluation committee 、 economic “ Expert database ”
3、 The total calendar days of the construction contract period are those indicated in the letter of acceptance (B) Bidding duration .
A. Requirements of the bidding documents
B. The employer accepts
C. The engineer confirms that
D. The contractor appoints
4、 The contents that do not belong to the supervisor's obligations in the entrusted supervision contract are (C)
A. Safeguard the legitimate rights and interests of relevant parties fairly
B. Send enough personnel to engage in supervision work
C. Complete the additional work and extra work proposed by the client
D. Be responsible for the coordination and management of the contract
5、 The supervision engineer is based on (C) Inspect the project quality of the contractor according to the quality standard of the contractor .
A. Laws and regulations
B. National mandatory
C. The contract stipulates that
D. The location of the project
6、 Contracts concluded due to major misunderstandings , A party has the right to (A)
A. Request the people's court to revoke
B. Request the people's court to confirm the invalidity
C. Terminate a contract
D. Change the contract
7、 In order to ensure the project quality ,《 Construction contract of construction project ( Model text )》 Regulations (A) The minimum quality warranty period is 5 year .
A. Waterproofing works
B. Water supply pipeline works
C. Equipment installation engineering
D. Foundation engineering
8、 A construction contract stipulates that the contracted project shall be completed on 9 month 20 Date of completion .8 Found in the middle of August , Because the Contractor's construction management is not strict , The actual progress lags behind the planned progress . The contractor modified the schedule as required by the engineer , The completion date is postponed to 9 month 30 Japan . The schedule has been confirmed by the engineer , be (B)
A. If you rush through work in 9 month 20 Date of completion , Award for early completion
B. If you rush through work in 9 month 20 Date of completion , No award for early completion
C. If in 9 month 25 Date of completion , Neither get a reward , Nor is it liable for delay
D. If in 9 month 30 Date of completion , No liability for delay
9、 After the construction enterprise borrows money from the bank with its own assets as collateral , Unable to repay due to the rupture of the capital chain , When the property was auctioned according to law, it owed the bank 500 Ten thousand yuan principal 、20 Ten thousand yuan interest 、50 Liquidated damages of ten thousand yuan , Proceeds from auction of real estate 400 Ten thousand yuan , Auction fees l0 Ten thousand yuan , Then the debt owed by the construction enterprise to the bank (D)
A. Destroy all
B. also 100 Ten thousand yuan
C. also 150 Ten thousand yuan
D. also 180 Ten thousand yuan
10、 The material procurement contract is being performed , The method that can be used to accept the quantity of materials delivered on site is (A)
A. Measurement method
B. Empirical identification
C. Physical test method
D. Chemical analysis
Above is 2022 Practice questions and answers of supervision engineer contract management in , Youtibao will continue to update the real problems, simulation problems and answer analysis of supervision engineer's contract management , Candidates, if necessary , Don't miss it . I also hope that all candidates can achieve good results in the contract management of supervision engineers .

版权声明
本文为[Laughing at online classes]所创,转载请带上原文链接,感谢
https://yzsam.com/2022/04/202204211229380398.html
边栏推荐
- Blazor 的 NavLink 的 NavLinkMatch.Prefix 有啥作用
- 【数字信号处理】相关系数 ( 相关系数概念 | 能量信号与功率信号 | 系统的因果性 )
- The difference between thread library and ASIO Library
- Analysis of several major reasons for the slow use of computers
- 北京大学ACM Problems 1008:Maya Calendar
- twenty million two hundred and ten thousand eight hundred and twelve
- Navlinkmatch of blazor's navlink What does prefix do
- 53W words! Ali's first system performance optimization guide is so fragrant that it can be called the optimal solution of performance optimization
- PostgreSQL 15 will soon support merge statements in the SQL standard
- Tailwind核心理念——响应式设计
猜你喜欢

科技巨头竞相入场,谁能成为元宇宙“头号玩家”?
![leetcode:513. Find the value in the lower left corner of the tree [simply BFS find the first one in each layer]](/img/be/d026b15f89f39944cf03aa0a05d9e3.png)
leetcode:513. Find the value in the lower left corner of the tree [simply BFS find the first one in each layer]

Could not load dynamic library ‘libcusolver.so.11‘
![BUUCTF [第三章 web进阶]逻辑漏洞](/img/fb/99a5c60979970a9d6cd0fe0e0fb7a4.png)
BUUCTF [第三章 web进阶]逻辑漏洞

【csnote】db异常(冗余数据、修改异常、删除异常、插入异常)

前馈神经网络

Last online class can be "distracted" by AI analysis. Intel's emotional detection AI is on fire

Fibonacci sequence

Industry video super resolution new benchmark, Kwai & Dalian research, boarded CVPR 2022

Tailwind核心理念——响应式设计
随机推荐
Wang Baiping: my way to envoy maintainer
跑步运动耳机哪个牌子好、适合运动的耳机
Underlying principle of high concurrent IO
Skills of layout design
leetcode:513. 找树左下角的值【简单bfs找每层第一个】
Baidu map development custom information window openinfowindow style
CV technical guide free knowledge planet
Sliding window series - find minimum overlay string
百度地图开发自定义信息窗口openInfoWindow样式
必选项输入内容后红色星号消失
thread库和 asio 库区别
通讯录的动态实现
An example of expert system and its skeleton system
科技巨头竞相入场,谁能成为元宇宙“头号玩家”?
前馈神经网络
北京大学ACM Problems 1012:Maya Calendar
MySQL使用安装pip和binlog2sql
【數字信號處理】相關系數 ( 相關系數概念解析 | 信號能量常數 | 共軛序列 | 序列在相同時刻的相關性 )
被迫选择了到了外包公司
Idea automatically generates unit test classes