当前位置:网站首页>Mba-day5 Mathematics - application problems - engineering problems
Mba-day5 Mathematics - application problems - engineering problems
2022-04-23 10:55:00 【Fadi】
1. Basic knowledge points
1.1 workload s, The work efficiency v, working hours t The relationship among the three
- workload = The work efficiency * working hours namely s = vt
- working hours = workload / The work efficiency namely t = s/v
- The work efficiency = workload / Time , namely v = s/t
Important note : Time t A certain , Efficiency is directly proportional to the total
1.2 Important conclusions
If Party A completes it alone, it needs m God , Party B needs to complete it alone n God , be
-
- The efficiency of a is 1/m, The efficiency of B is 1/n
-
- The efficiency of cooperation between Party A and Party B is : 1/m + 1/n ( Efficiency can be added or subtracted )
-
- The time required for the completion of the cooperation between Party A and Party B is 1 /(1/m + 1/n)= mn / (m+n)
1.3 Train of thought
Encountered engineering quantity problems , Generally, the whole engineering quantity is ( Water discharge capacity ) See the unit 1, Then solve the problem proportionally according to the problem stem conditions .
It is usually assumed that the total amount ( The amount of work 、 Water discharge capacity )= 1 Analyze
-【 Important formula 】 Total efficiency = Each efficiency algebra and
- The work efficiency = workload / working hours
- Total amount = Partial quantity / Its corresponding proportion
2. Example
- Example 1: Build a highway , Team a's separate construction requires 40 Days to complete , Team B needs to work alone 24 Days to complete , Now both teams are from 2 End start , The result is at the midpoint of the distance 7.5 km Meeting and completion , Then the length of this highway is ()km
Explain : Set the length of this highway s km
Construction by team a alone requires 40 Days to complete , The efficiency of team a is s / 40
Construction by team B alone requires 24 Days to complete , The efficiency of team B is s / 24
From now on, the two teams start from 2 End start , The result is at the midpoint of the distance 7.5 km Meeting and completion
1. From the efficiency, we know that team B is the most efficient
2. A and B are at the midpoint of the distance 7.5 km Meeting and completion , It means that this period of time is the same
3. The construction length of Party A is s/2 - 7.5 km, The construction length of team B is s/2 + 7.5 km
Therefore, the following relationship is obtained : Time = workload / efficiency
(s/2 - 7.5) / (s / 40) = (s/2 + 7.5)/ (s / 24)
(s/2 - 7.5) * (s / 24) = (s / 40) * (s/2 + 7.5)
(s/2 - 7.5) * (1/24) = (1 / 40) *(s/2 + 7.5)
(1/24) / (1 / 40) = (s/2 + 7.5)/ (s/2 - 7.5)
5/3 = (s/2 + 7.5)/ (s/2 - 7.5)
s = 60 km
- Example 2: A project is jointly undertaken by Party A and Party B 30 Days can be done , Team a does it alone 24 Days later , Team B joins , The two teams work together 10 Days later , Team a transferred , Team B continued to do 17 Finish... In days . If the project is done by team a alone , You need to () God
Explain :
According to the workload = working hours * The work efficiency
Let the working efficiency of Party A be x, B. the working efficiency is y, The following relationships can be obtained quickly
30x + 30y = workload
34x + 27y = workload
y = 4/3 x
Bring the above proportion into : nail 30 + B 30 = Quantities completed
30x + 30 * 4/3 x = workload
70x = workload
70 = workload /x = working hours
- Example 3: A unit carries out office decoration , If Party A and Party B cooperate , Need to be 10 Zhou finished . The man hour fee is 100 ten thousand , Company a first does 6 Company B will continue to do it in a week 18 Zhou finished , The man hour fee is 96 ten thousand , Ask company a for the weekly man hour cost ()
Explain , Weekly man hour cost of company A x, Company B's weekly man hour expenses y
If Party A and Party B cooperate , Need to be 10 Zhou finished . The man hour fee is 100 ten thousand , have to 10x+10y = 100
Company a will do it first 6 Company B will continue to do it in a week 18 Zhou finished , The man hour fee is 96 ten thousand , have to 6x+18y=96
10x+10y = 100
6x+18y=96
The most simplified is
x+y =10
x+3y=16
have to y =3, x =7, That is, the weekly man hour cost of company A 7 ten thousand
版权声明
本文为[Fadi]所创,转载请带上原文链接,感谢
https://yzsam.com/2022/04/202204231053145929.html
边栏推荐
猜你喜欢

Swagger2 接口如何导入Postman

Visualization Road (10) detailed explanation of segmentation canvas function

C language - custom type

Jinglianwen technology - professional data annotation company and intelligent data annotation platform

Reading integrity monitoring techniques for vision navigation systems - 3 background

解决方案架构师的小锦囊 - 架构图的 5 种类型

STM32接电机驱动,杜邦线供电,然后反烧问题

使用zerotier让异地设备组局域网

SQL Server 游标循环表数据

Intuitive understanding entropy
随机推荐
SSH uses private key to connect to server without key
997. Square of ordered array (array)
SQL Server 递归查询上下级
Solutions to common problems in visualization (VIII) solutions to problems in shared drawing area
【leetcode】102.二叉树的层序遍历
Problems of class in C # and database connection
得到知识服务app原型设计比较与实践
24. Exchange the nodes in the linked list (linked list)
Detailed explanation of typora Grammar (I)
Restful、SOAP、RPC、SOA、微服务之间的区别
Leetcode22: bracket generation
MBA-day5数学-应用题-工程问题
微信小程序简介、发展史、小程序的优点、申请账号、开发工具、初识wxml文件和wxss文件
Precautions for latex formula
Pytorch implementation of transformer
Google Earth Engine(GEE)——将原始影像进行升尺度计算(以海南市为例)
SWAT - Introduction to Samba web management tool
Learning notes 7-depth neural network optimization
比深度学习更值得信赖的模型ART
C#和数据库连接中类的问题