当前位置:网站首页>Mba-day5 Mathematics - application problems - engineering problems
Mba-day5 Mathematics - application problems - engineering problems
2022-04-23 10:55:00 【Fadi】
1. Basic knowledge points
1.1 workload s, The work efficiency v, working hours t The relationship among the three
- workload = The work efficiency * working hours namely s = vt
- working hours = workload / The work efficiency namely t = s/v
- The work efficiency = workload / Time , namely v = s/t
Important note : Time t A certain , Efficiency is directly proportional to the total
1.2 Important conclusions
If Party A completes it alone, it needs m God , Party B needs to complete it alone n God , be
-
- The efficiency of a is 1/m, The efficiency of B is 1/n
-
- The efficiency of cooperation between Party A and Party B is : 1/m + 1/n ( Efficiency can be added or subtracted )
-
- The time required for the completion of the cooperation between Party A and Party B is 1 /(1/m + 1/n)= mn / (m+n)
1.3 Train of thought
Encountered engineering quantity problems , Generally, the whole engineering quantity is ( Water discharge capacity ) See the unit 1, Then solve the problem proportionally according to the problem stem conditions .
It is usually assumed that the total amount ( The amount of work 、 Water discharge capacity )= 1 Analyze
-【 Important formula 】 Total efficiency = Each efficiency algebra and
- The work efficiency = workload / working hours
- Total amount = Partial quantity / Its corresponding proportion
2. Example
- Example 1: Build a highway , Team a's separate construction requires 40 Days to complete , Team B needs to work alone 24 Days to complete , Now both teams are from 2 End start , The result is at the midpoint of the distance 7.5 km Meeting and completion , Then the length of this highway is ()km
Explain : Set the length of this highway s km
Construction by team a alone requires 40 Days to complete , The efficiency of team a is s / 40
Construction by team B alone requires 24 Days to complete , The efficiency of team B is s / 24
From now on, the two teams start from 2 End start , The result is at the midpoint of the distance 7.5 km Meeting and completion
1. From the efficiency, we know that team B is the most efficient
2. A and B are at the midpoint of the distance 7.5 km Meeting and completion , It means that this period of time is the same
3. The construction length of Party A is s/2 - 7.5 km, The construction length of team B is s/2 + 7.5 km
Therefore, the following relationship is obtained : Time = workload / efficiency
(s/2 - 7.5) / (s / 40) = (s/2 + 7.5)/ (s / 24)
(s/2 - 7.5) * (s / 24) = (s / 40) * (s/2 + 7.5)
(s/2 - 7.5) * (1/24) = (1 / 40) *(s/2 + 7.5)
(1/24) / (1 / 40) = (s/2 + 7.5)/ (s/2 - 7.5)
5/3 = (s/2 + 7.5)/ (s/2 - 7.5)
s = 60 km
- Example 2: A project is jointly undertaken by Party A and Party B 30 Days can be done , Team a does it alone 24 Days later , Team B joins , The two teams work together 10 Days later , Team a transferred , Team B continued to do 17 Finish... In days . If the project is done by team a alone , You need to () God
Explain :
According to the workload = working hours * The work efficiency
Let the working efficiency of Party A be x, B. the working efficiency is y, The following relationships can be obtained quickly
30x + 30y = workload
34x + 27y = workload
y = 4/3 x
Bring the above proportion into : nail 30 + B 30 = Quantities completed
30x + 30 * 4/3 x = workload
70x = workload
70 = workload /x = working hours
- Example 3: A unit carries out office decoration , If Party A and Party B cooperate , Need to be 10 Zhou finished . The man hour fee is 100 ten thousand , Company a first does 6 Company B will continue to do it in a week 18 Zhou finished , The man hour fee is 96 ten thousand , Ask company a for the weekly man hour cost ()
Explain , Weekly man hour cost of company A x, Company B's weekly man hour expenses y
If Party A and Party B cooperate , Need to be 10 Zhou finished . The man hour fee is 100 ten thousand , have to 10x+10y = 100
Company a will do it first 6 Company B will continue to do it in a week 18 Zhou finished , The man hour fee is 96 ten thousand , have to 6x+18y=96
10x+10y = 100
6x+18y=96
The most simplified is
x+y =10
x+3y=16
have to y =3, x =7, That is, the weekly man hour cost of company A 7 ten thousand
版权声明
本文为[Fadi]所创,转载请带上原文链接,感谢
https://yzsam.com/2022/04/202204231053145929.html
边栏推荐
- Leetcode22: bracket generation
- Intuitive understanding entropy
- 得到知识服务app原型设计比较与实践
- Windows installs redis and sets the redis service to start automatically
- 精彩回顾|「源」来如此 第六期 - 开源经济与产业投资
- Gets the current time in character format
- 关于JUC三大常用辅助类
- 203. Remove linked list elements (linked list)
- 454. Sum of four numbers (hash table)
- Learning notes 7-depth neural network optimization
猜你喜欢

Let the LAN group use the remote device

得到知识服务app原型设计比较与实践

解决方案架构师的小锦囊 - 架构图的 5 种类型

Source insight 4.0 FAQs

SQL Server cursor circular table data

VIM + ctags + cscope development environment construction guide

Reading integrity monitoring techniques for vision navigation systems - 3 background

Comparison and practice of prototype design of knowledge service app

Visual common drawing (I) stacking diagram

Intuitive understanding entropy
随机推荐
UEditor之——图片上传组件大小4M的限制
使用 PHP PDO ODBC 示例的 Microsoft Access 数据库
SQL Server recursive query of superior and subordinate
Learning notes 7-depth neural network optimization
Reading integrity monitoring techniques for vision navigation systems - 3 background
Understand the key points of complement
Comparison and practice of prototype design of knowledge service app
微信小程序简介、发展史、小程序的优点、申请账号、开发工具、初识wxml文件和wxss文件
Construction and traversal of binary tree
【leetcode】102.二叉树的层序遍历
Initial exploration of NVIDIA's latest 3D reconstruction technology instant NGP
203. Remove linked list elements (linked list)
高价买来的课程,公开了!phper资料分享
Chapter 1 of technical Xiaobai (express yourself)
《Neo4j权威指南》简介,求伯君、周鸿袆、胡晓峰、周涛等大咖隆重推荐
VIM usage
Visualization Road (11) detailed explanation of Matplotlib color
Windows installs redis and sets the redis service to start automatically
Learning note 5 - gradient explosion and gradient disappearance (k-fold cross verification)
Comparison and practice of prototype design of knowledge service app