当前位置:网站首页>Question bank and answer analysis of the 2022 simulated examination of the latest eight members of Jiangxi construction (quality control)
Question bank and answer analysis of the 2022 simulated examination of the latest eight members of Jiangxi construction (quality control)
2022-04-23 13:47:00 【100% question bank app】
The 100% question bank provides Building eight ( Quality controller ) Examination questions 、 Building eight ( Quality controller ) Test prediction questions 、 Building eight ( Quality controller ) The real exam question 、 Building eight ( Quality controller ) Certificate examination question bank, etc , Provide online questions and brush questions , Online mock exam , Help you pass the exam easily .

411 Time for concrete watering and curing : For the use of Portland cement 、 Ordinary portland cement or Portland slag concrete , Not less than ().
A.7d
B.10d
C.5d
D.14d
answer :A
412 When the effective control range of the project manager exceeds its ability , need ().
A. Reduce the level of Management , Increase the scope of Management
B. Reduce the level of Management , Reduce the scope of management
C. Increase management level , Reduce the scope of management
D. Reduce the number of superior departments
answer :C
413 Organization scale in engineering project management usually refers to the size of the organization ()
A. Office space
B. The registered capital
C. Number of departments
D. Number of people
answer :D
414 The number of subordinate personnel directly led by the manager of the project management organization is called ()
A. Management range
B. Management functions
C. Management scale
D. Management procedure
answer :A
415 To ensure the quality of the construction project , The process control of construction projects should be strengthened , Carry out the three inspection system , It mainly refers to ()
A. The Quality Inspector checks 、 Check by the technical director 、 The project manager checks
B. Inspection by the construction unit 、 Inspection by the supervision unit 、 Inspection by the employer
C. Internal inspection of construction unit 、 Inspection by the supervision unit 、 Inspection by quality supervision organization
D. Self inspection 、 Mutual inspection 、 Special inspection
answer :D
416 The task of construction project quality control is ()
A. Reasonably arrange the construction process , Complete the contract construction period ahead of schedule B. Ensure the realization of the contract quality objective level
C. Achieve the company's profit target
D. Make fire protection 、 Environmental protection meets the specified requirements
answer :B
417 In the following options , The economic measures that belong to the objective control of the construction project are ().
A. Establish a working system for progress control
B. Adjust the logical relationship between
C. Establish and implement progress reward and punishment system
D. Adopt new technology 、 New technology
answer :C
418 Only objects can move in any direction , A support that does not restrict the rotation of an object is called () Bearing .
A. Fixed hinge
B. Movable hinge
C. Fixed end
D. Smooth surface
answer :A
419 The unit of torque is ().
A.kN·m
B.kN/m
C.kN
D.N
answer :A
420 The stress analysis of multi span statically determinate beam follows the first (), after () The sequence of analysis .
A. Subsidiary parts , The basic part
B. The basic part , Subsidiary parts
C. whole , Local
D. Local , whole
answer :A

421 The greater the stress, the greater the strain ()
A. Big
B. Small
C. not always
D. unchanged
answer :A
422 Stress is the internal force in () Distribution set of .
A. At some point
B. One side
C. A few points
D. Several sides
answer :A
423 The greater the flexibility of the compression bar , The more stable the compression bar is ().
A. Bad
B. good
C. very good
D. Big
answer :A
424 The requirement to limit excessive deformation is () requirement .
A. bending
B. stiffness
C. deflection
D. Reverse
answer :B
425 It is assumed that the mechanical properties of the internal parts of the solid are the same everywhere , by ().
A. Uniformity assumption
B. Continuity assumption
C. Isotropic hypothesis
D. Small deformation hypothesis
answer :A
426 With an axis () The deformation form that is the main feature is called bending deformation or bending for short .
A. Bend
B. Variable shear
C. Variable tension
D. Twist
answer :A
427 The outer side of the vertical waterproof coiled material of the basement wall is generally made after the cement mortar protective layer is completed ().
A.500mm Wide water resisting layer
B.500mm Wide filter layer
C. One coat of cold primer oil and two coats of hot asphalt
D. Brick protective wall
answer :D
428 The rib height of well shaped multi ribbed floor slab is generally ().
A.90~120mm
B.120~150mm
C.120mm
D.180~250 mm
answer :D
429 The coating waterproof structure of flat roof can be divided into positive type and inverted type , The so-called positive form refers to ().
A. The thermal insulation layer is above the coating waterproof layer
B. The thermal insulation layer is above the leveling layer
C. The thermal insulation layer is under the coating waterproof layer
D. The base treatment agent is under the leveling layer
answer :C
430 Hard and wear-resistant 、 The decoration effect is good 、 The cost is high , It is generally applicable to rooms with water and rooms with corrosion. The decorative structure of the floor is ()
A. Cement mortar floor
B. Terrazzo floor
C. Ceramic plate floor
D. Artificial slate floor
answer :C
431 In the connection method of steel structure ,() It is simple in structure , Save steel , Easy processing , Easy to adopt automatic operation .
A. High strength bolt connection
B. Rivet connection
C. Welded connection
D. Common bolted connection
answer :A
432 In Architecture ,() Mainly used as roof panel 、 Wallboard 、 Floor and decorative panels, etc .
A. steel strip
B. Color coated steel plate
C. Checkered steel plate
D. Profiled steel sheet
answer :D
433 The following statement about the graphic method of the general plan of the building , The wrong is ().
A. The general plan of the building is a horizontal projection within a certain range of the area where the new house is located
B. The general plan of the building is a new building within a certain range around the proposed project 、 Proposed 、 Existing and buildings to be demolished 、 The structure and its surrounding terrain and features , A pattern drawn by horizontal projection .
C. As the plot scale of the general layout is small , The original house in the picture 、 road 、 greening 、 Bridge slope 、 Walls and new houses are represented by legends
D. The legend of the demolished building is quadrilateral
answer :D
版权声明
本文为[100% question bank app]所创,转载请带上原文链接,感谢
https://yzsam.com/2022/04/202204231337061133.html
边栏推荐
- Oracle RAC database instance startup exception analysis IPC send timeout
- 零拷贝技术
- Innobackupex incremental backup
- Lenovo Savior y9000x 2020
- Tersus notes employee information 516 MySQL query (time period uniqueness judgment of 2 fields)
- Ai21 labs | standing on the shoulders of giant frozen language models
- 剑南春把文字游戏玩明白了
- Influence of openssh version on SSH mutual trust creation in RAC environment
- Get the attribute value difference between two different objects with reflection and annotation
- Analysis of cluster component gpnp failed to start successfully in RAC environment
猜你喜欢

Search ideas and cases of large amount of Oracle redo log
![MySQL index [data structure + index creation principle]](/img/11/6bdc8a62e977ffb67be07ded0c8978.png)
MySQL index [data structure + index creation principle]
![MySQL [read / write lock + table lock + row lock + mvcc]](/img/a9/ace85899a01a7d4fd80b2e631e44d6.png)
MySQL [read / write lock + table lock + row lock + mvcc]

Unified task distribution scheduling execution framework

Modify the Jupiter notebook style

UML统一建模语言

10g database cannot be started when using large memory host

自动化的艺术

顶级元宇宙游戏Plato Farm,近期动作不断利好频频

Express中间件③(自定义中间件)
随机推荐
Window analysis function last_ VALUE,FIRST_ VALUE,lag,lead
Plato farm, a top-level metauniverse game, has made frequent positive moves recently
Detailed explanation of redis (Basic + data type + transaction + persistence + publish and subscribe + master-slave replication + sentinel + cache penetration, breakdown and avalanche)
Oracle lock table query and unlocking method
Oracle modify default temporary tablespace
Dolphin scheduler integrates Flink task pit records
Dolphin scheduler configuring dataX pit records
10g database cannot be started when using large memory host
Generate 32-bit UUID in Oracle
Express中间件③(自定义中间件)
NPM err code 500 solution
Move blog to CSDN
Ora-16047 of a DG environment: dgid mismatch between destination setting and target database troubleshooting and listening vncr features
【vmware】vmware tools 地址
Solution: you have 18 unapplied migration (s) Your project may not work properly until you apply
Resolution: argument 'radius' is required to be an integer
GDB的使用
Detailed explanation of Oracle tablespace table partition and query method of Oracle table partition
AI21 Labs | Standing on the Shoulders of Giant Frozen Language Models(站在巨大的冷冻语言模型的肩膀上)
Explanation of input components in Chapter 16