当前位置:网站首页>Chapter IV project cost management of information system project manager summary
Chapter IV project cost management of information system project manager summary
2022-04-23 02:50:00 【Chen junyang】
《 Summary of information system project manager 》 Chapter four Project cost management
Catalog
- 《 Summary of information system project manager 》 Chapter four Project cost management
- One 、 Planning cost management
- Two 、 Estimated cost
- 3、 ... and 、 Budget making
- Four 、 Control the cost
Ten management contents of information system project manager .
Four 、 Project cost management
1、 Planning cost management
2、 Estimated cost
3、 Budget making
4、 Control the cost
One 、 Planning cost management
Planning cost management is for planning 、 management 、 Spend and control project costs and make policies 、 Procedures and documentation , The main function of this process is , Provide guidance and direction on how to manage project costs throughout the project .
>>> Input :
1、 Project management plan
2、 Project Charter
3、 Business environment factors
4、 Organizational process assets
>>> Tools and Technology :
1、 Expert judgment
2、 Analytical techniques
3、 meeting
>>> Output :
1、 Cost management plan
The cost management plan is an integral part of the project management plan , Describe how it will be planned 、 Arrange and control project cost .
Two 、 Estimated cost
Cost estimation is the process of approximate estimation of the funds required to complete the project activities . The main function of this process is , Determine the amount of cost required to complete the project work .
The main steps of project cost estimation , The preparation of project cost estimation requires the following three main steps .
(1) Identify and analyze cost components .
(2) Accounts are formed according to the identified project cost , Estimate the cost of each account .
(3) Analyze the cost estimation results , Find various alternative costs , Coordinate the proportional relationship between various costs .
>>> Input :
1、 Cost management plan
2、 Human resource management plan
3、 Range reference
Include scope statement 、 Work breakdown structure 、WBS The dictionary .
4、 Project schedule
5、 Risk register
6、 Business environment factors
7、 Organizational process assets
>>> Tools and Technology :
1、 Expert judgment
2、 Analogous estimating
When project details are insufficient , For example, in the early stages of a project , This technique is often used to estimate the cost value . Analogical estimation is usually cheaper 、 Less time consuming , But the accuracy is also low .
3、 Parameter estimation
Parameter estimation refers to the cost estimation of project work by using the statistical relationship between historical data and other variables . The accuracy of parameter estimation depends on the maturity of parameter model and the reliability of basic data . Parameter estimation can be for the whole project or a part of the project , It can be used in combination with other estimation methods .
4、 Three point estimation
5、 Bottom-up estimating
Bottom up estimation is a way to estimate the components of a job . First, the cost of a single work package or activity is analyzed in detail 、 Careful estimation ; And then aggregate these detailed costs up or “ rolling ” To a higher level , For follow-up reporting and tracking . The accuracy of bottom-up estimation and its own cost , It usually depends on the size and complexity of a single activity or work package .
6、 Group decision making technology
7、 Reserve analysis
8、 quality cost
9、 Project management software
10、 Seller's bid analysis
In the process of cost estimation , It may need to be based on the bidding situation of qualified sellers , Analyze project cost .
>>> Output :
1、 Activity cost estimates
A quantitative estimate of the cost that may be required to complete the project work .
2、 Estimation basis
Quantity and type of supporting information required for cost estimation .
3、 Project file update
3、 ... and 、 Budget making
Budgeting is to summarize the estimated costs of all individual activities or work packages , The process of establishing an approved cost baseline . The main function of this process is , Set a cost benchmark , Project performance can be monitored and controlled accordingly .
The project budget includes all funds approved for the project . The cost baseline is the approved project budget allocated by time period , But it doesn't include managing reserves .
>>> Input :
1、 Cost management plan
2、 Range reference
3、 Activity cost estimates
4、 Estimation basis
5、 Project schedule
6、 Resource Calendar
7、 Risk register
8、 agreement
9、 Organizational process assets
>>> Tools and Technology :
1、 Cost summary
First, summarize the cost estimate to WBS Work packages in , From work package to WBS Higher level ( Such as control account ), Finally get the total cost of the whole project .
2、 Reserve analysis
3、 Expert judgment
4、 Historical relations
There may be some historical relationships between relevant variables that can be used for parameter estimation or analogy estimation . Based on these historical relationships , Use project features ( Parameters ) To build a mathematical model , Forecast the total cost of the project .
5、 Resource restriction balance
Should be based on any restrictions on project funding , To balance financial support . If you find a difference between the capital limit and the planned expenditure , The work schedule may need to be adjusted , To balance the level of capital expenditure . This can be achieved by adding mandatory dates to the project schedule .
>>> Output :
1、 Cost basis
The cost baseline is approved 、 Project budget allocated by time period , Excluding any management reserves , Changes can only be made through formal change control procedures , Used as a basis for comparison with actual results . Cost benchmark is the sum of approved budgets for different schedule activities . Increase the management reserve above the cost benchmark , Get the project budget .
2、 Project funding requirements
3、 Project file update
Four 、 Control the cost
Cost control is to monitor project status , To update project costs , The process of managing cost baseline changes . The main function of this process is , Find the difference between actual and planned , In order to take corrective measures , Reduce risk .
Project cost control includes :
(1) Influence the factors causing the change of cost benchmark .
(2) Ensure that all change requests are processed in a timely manner .
(3) When the change actually occurs , Manage these changes .
(4) Ensure that the cost does not exceed the approved funding limit , Not beyond the time period 、 Press WBS Components 、 Quota by activity , No more than the total project quota .
(5) Monitor cost performance , Identify and analyze deviations from the cost base .
(6) Compared with financial support , Monitor job performance .
(7) Prevent unauthorized changes in cost or resource usage reports .
(8) Report all approved changes and related costs to relevant stakeholders .
(9) Try to control the expected cost overrun within an acceptable range .
>>> Input :
1、 Project management plan
2、 Project funding requirements
3、 Performance data
4、 Organizational process assets
>>> Tools and Technology :
1、 Earned value management
2、 forecast
3、 to complete performance index (TCPI)
4、 Performance review
The objects of performance review include : Cost performance changes over time 、 Progress activities or work packages exceeding and below budget , And an estimate of the funds needed to complete the work .
5、 Project management software
6、 Reserve analysis
>>> Output :
1、 Job performance information
2、 Cost forecast
3、 Change request
4、 Project management plan update
5、 Project file update
6、 Organizational process asset update
版权声明
本文为[Chen junyang]所创,转载请带上原文链接,感谢
https://yzsam.com/2022/04/202204230247086762.html
边栏推荐
- The input of El input input box is invalid, and error in data(): "referenceerror: El is not defined“
- [hcip] detailed explanation of six LSAS commonly used by OSPF
- ele之Table表格的封装
- [XJTU計算機網絡安全與管理]第二講 密碼技術
- Cuisine leetcode
- Windows MySQL 8 zip installation
- 高效音乐格式转换工具Music Converter Pro
- Log cutting - build a remote log collection server
- Preliminary understanding of stack and queue
- Planning code ROS migration POMDP prediction planning (I)
猜你喜欢
Hack the box optimum
[XJTU计算机网络安全与管理]第二讲 密码技术
[wechat applet] set the bottom menu (tabbar) for the applet
重大危险源企业如何保障年底前完成双预防机制数字化建设任务
The input of El input input box is invalid, and error in data(): "referenceerror: El is not defined“
Fashion MNIST 数据集分类训练
JVM运行时数据区(一)
期中汇总(概论+应用层+运输层)
Android 高阶面试必问:全局业务和项目的架构设计与重构
基于多态的职工管理系统源码与一些理解
随机推荐
基于Torchserve部署SBERT模型<语义相似度任务>
Log4j知识点记录
Fashion MNIST dataset classification training
基于ele封装下拉菜单等组件
[hcip] detailed explanation of six LSAS commonly used by OSPF
Get together to watch (detailed version) eat a few cents a day
工业互联网+危化安全生产综合管理平台怎样建
Shell script learning -- practical case
[XJTU计算机网络安全与管理]第二讲 密码技术
学习正则表达式选项、断言
Suggestion: block reference sorting is in the order of keywords
MySQL insert free column
How to solve the complexity of project document management?
《信息系统项目管理师总结》第四章 项目成本管理
【unity3D】直播间滚动式弹幕效果
谷雨
C语言 171. 最近回文数
重大危险源企业如何保障年底前完成双预防机制数字化建设任务
Rhcsa day 4 operation
Devil cold rice 𞓜 078 devil answers the market in Shanghai and Nanjing; Communication and guidance; Winning the country and killing and screening; The purpose of making money; Change other people's op