当前位置:网站首页>Mba-day5 Mathematics - application problems - engineering problems
Mba-day5 Mathematics - application problems - engineering problems
2022-04-23 10:55:00 【Fadi】
1. Basic knowledge points
1.1 workload s, The work efficiency v, working hours t The relationship among the three
- workload = The work efficiency * working hours namely s = vt
- working hours = workload / The work efficiency namely t = s/v
- The work efficiency = workload / Time , namely v = s/t
Important note : Time t A certain , Efficiency is directly proportional to the total
1.2 Important conclusions
If Party A completes it alone, it needs m God , Party B needs to complete it alone n God , be
-
- The efficiency of a is 1/m, The efficiency of B is 1/n
-
- The efficiency of cooperation between Party A and Party B is : 1/m + 1/n ( Efficiency can be added or subtracted )
-
- The time required for the completion of the cooperation between Party A and Party B is 1 /(1/m + 1/n)= mn / (m+n)
1.3 Train of thought
Encountered engineering quantity problems , Generally, the whole engineering quantity is ( Water discharge capacity ) See the unit 1, Then solve the problem proportionally according to the problem stem conditions .
It is usually assumed that the total amount ( The amount of work 、 Water discharge capacity )= 1 Analyze
-【 Important formula 】 Total efficiency = Each efficiency algebra and
- The work efficiency = workload / working hours
- Total amount = Partial quantity / Its corresponding proportion
2. Example
- Example 1: Build a highway , Team a's separate construction requires 40 Days to complete , Team B needs to work alone 24 Days to complete , Now both teams are from 2 End start , The result is at the midpoint of the distance 7.5 km Meeting and completion , Then the length of this highway is ()km
Explain : Set the length of this highway s km
Construction by team a alone requires 40 Days to complete , The efficiency of team a is s / 40
Construction by team B alone requires 24 Days to complete , The efficiency of team B is s / 24
From now on, the two teams start from 2 End start , The result is at the midpoint of the distance 7.5 km Meeting and completion
1. From the efficiency, we know that team B is the most efficient
2. A and B are at the midpoint of the distance 7.5 km Meeting and completion , It means that this period of time is the same
3. The construction length of Party A is s/2 - 7.5 km, The construction length of team B is s/2 + 7.5 km
Therefore, the following relationship is obtained : Time = workload / efficiency
(s/2 - 7.5) / (s / 40) = (s/2 + 7.5)/ (s / 24)
(s/2 - 7.5) * (s / 24) = (s / 40) * (s/2 + 7.5)
(s/2 - 7.5) * (1/24) = (1 / 40) *(s/2 + 7.5)
(1/24) / (1 / 40) = (s/2 + 7.5)/ (s/2 - 7.5)
5/3 = (s/2 + 7.5)/ (s/2 - 7.5)
s = 60 km
- Example 2: A project is jointly undertaken by Party A and Party B 30 Days can be done , Team a does it alone 24 Days later , Team B joins , The two teams work together 10 Days later , Team a transferred , Team B continued to do 17 Finish... In days . If the project is done by team a alone , You need to () God
Explain :
According to the workload = working hours * The work efficiency
Let the working efficiency of Party A be x, B. the working efficiency is y, The following relationships can be obtained quickly
30x + 30y = workload
34x + 27y = workload
y = 4/3 x
Bring the above proportion into : nail 30 + B 30 = Quantities completed
30x + 30 * 4/3 x = workload
70x = workload
70 = workload /x = working hours
- Example 3: A unit carries out office decoration , If Party A and Party B cooperate , Need to be 10 Zhou finished . The man hour fee is 100 ten thousand , Company a first does 6 Company B will continue to do it in a week 18 Zhou finished , The man hour fee is 96 ten thousand , Ask company a for the weekly man hour cost ()
Explain , Weekly man hour cost of company A x, Company B's weekly man hour expenses y
If Party A and Party B cooperate , Need to be 10 Zhou finished . The man hour fee is 100 ten thousand , have to 10x+10y = 100
Company a will do it first 6 Company B will continue to do it in a week 18 Zhou finished , The man hour fee is 96 ten thousand , have to 6x+18y=96
10x+10y = 100
6x+18y=96
The most simplified is
x+y =10
x+3y=16
have to y =3, x =7, That is, the weekly man hour cost of company A 7 ten thousand
版权声明
本文为[Fadi]所创,转载请带上原文链接,感谢
https://yzsam.com/2022/04/202204231053145888.html
边栏推荐
- 使用 PHP PDO ODBC 示例的 Microsoft Access 数据库
- Jinglianwen technology - professional data annotation company and intelligent data annotation platform
- Is the pointer symbol of C language close to variable type or variable name?
- 微信小程序中app.js文件、组件、api
- MySql常用语句
- GO接口使用
- 24. Exchange the nodes in the linked list (linked list)
- 得到知识服务app原型设计比较与实践
- 59. Spiral matrix (array)
- Learning Notes 6 - Summary of several deep learning convolutional neural networks
猜你喜欢
Visualization Road (10) detailed explanation of segmentation canvas function
解决方案架构师的小锦囊 - 架构图的 5 种类型
Visual common drawing (III) area map
Let the LAN group use the remote device
使用 PHP PDO ODBC 示例的 Microsoft Access 数据库
Visual common drawing (IV) histogram
SQL Server recursive query of superior and subordinate
Download and installation steps of xshell + xftp
部署jar包
26. 删除有序数组中的重复项
随机推荐
【leetcode】102.二叉树的层序遍历
Strongest date regular expression
454. Sum of four numbers (hash table)
图像处理——噪声小记
最强日期正则表达式
Learning notes 7-depth neural network optimization
我的创作纪念日
Typora operation skill description (I) md
MySQL how to merge the same data in the same table
Charles function introduction and use tutorial
解决方案架构师的小锦囊 - 架构图的 5 种类型
RESTful和SOAP的区别
UDP basic learning
Contact between domain name and IP address
MBA-day5數學-應用題-工程問題
一个微博数据库设计带来的简单思考
Differences among restful, soap, RPC, SOA and microservices
Arbitrary file reading vulnerability exploitation Guide
部署jar包
Deploy jar package