当前位置:网站首页>Mba-day5 Mathematics - application problems - engineering problems
Mba-day5 Mathematics - application problems - engineering problems
2022-04-23 10:55:00 【Fadi】
1. Basic knowledge points
1.1 workload s, The work efficiency v, working hours t The relationship among the three
- workload = The work efficiency * working hours namely s = vt
- working hours = workload / The work efficiency namely t = s/v
- The work efficiency = workload / Time , namely v = s/t
Important note : Time t A certain , Efficiency is directly proportional to the total
1.2 Important conclusions
If Party A completes it alone, it needs m God , Party B needs to complete it alone n God , be
-
- The efficiency of a is 1/m, The efficiency of B is 1/n
-
- The efficiency of cooperation between Party A and Party B is : 1/m + 1/n ( Efficiency can be added or subtracted )
-
- The time required for the completion of the cooperation between Party A and Party B is 1 /(1/m + 1/n)= mn / (m+n)
1.3 Train of thought
Encountered engineering quantity problems , Generally, the whole engineering quantity is ( Water discharge capacity ) See the unit 1, Then solve the problem proportionally according to the problem stem conditions .
It is usually assumed that the total amount ( The amount of work 、 Water discharge capacity )= 1 Analyze
-【 Important formula 】 Total efficiency = Each efficiency algebra and
- The work efficiency = workload / working hours
- Total amount = Partial quantity / Its corresponding proportion
2. Example
- Example 1: Build a highway , Team a's separate construction requires 40 Days to complete , Team B needs to work alone 24 Days to complete , Now both teams are from 2 End start , The result is at the midpoint of the distance 7.5 km Meeting and completion , Then the length of this highway is ()km
Explain : Set the length of this highway s km
Construction by team a alone requires 40 Days to complete , The efficiency of team a is s / 40
Construction by team B alone requires 24 Days to complete , The efficiency of team B is s / 24
From now on, the two teams start from 2 End start , The result is at the midpoint of the distance 7.5 km Meeting and completion
1. From the efficiency, we know that team B is the most efficient
2. A and B are at the midpoint of the distance 7.5 km Meeting and completion , It means that this period of time is the same
3. The construction length of Party A is s/2 - 7.5 km, The construction length of team B is s/2 + 7.5 km
Therefore, the following relationship is obtained : Time = workload / efficiency
(s/2 - 7.5) / (s / 40) = (s/2 + 7.5)/ (s / 24)
(s/2 - 7.5) * (s / 24) = (s / 40) * (s/2 + 7.5)
(s/2 - 7.5) * (1/24) = (1 / 40) *(s/2 + 7.5)
(1/24) / (1 / 40) = (s/2 + 7.5)/ (s/2 - 7.5)
5/3 = (s/2 + 7.5)/ (s/2 - 7.5)
s = 60 km
- Example 2: A project is jointly undertaken by Party A and Party B 30 Days can be done , Team a does it alone 24 Days later , Team B joins , The two teams work together 10 Days later , Team a transferred , Team B continued to do 17 Finish... In days . If the project is done by team a alone , You need to () God
Explain :
According to the workload = working hours * The work efficiency
Let the working efficiency of Party A be x, B. the working efficiency is y, The following relationships can be obtained quickly
30x + 30y = workload
34x + 27y = workload
y = 4/3 x
Bring the above proportion into : nail 30 + B 30 = Quantities completed
30x + 30 * 4/3 x = workload
70x = workload
70 = workload /x = working hours
- Example 3: A unit carries out office decoration , If Party A and Party B cooperate , Need to be 10 Zhou finished . The man hour fee is 100 ten thousand , Company a first does 6 Company B will continue to do it in a week 18 Zhou finished , The man hour fee is 96 ten thousand , Ask company a for the weekly man hour cost ()
Explain , Weekly man hour cost of company A x, Company B's weekly man hour expenses y
If Party A and Party B cooperate , Need to be 10 Zhou finished . The man hour fee is 100 ten thousand , have to 10x+10y = 100
Company a will do it first 6 Company B will continue to do it in a week 18 Zhou finished , The man hour fee is 96 ten thousand , have to 6x+18y=96
10x+10y = 100
6x+18y=96
The most simplified is
x+y =10
x+3y=16
have to y =3, x =7, That is, the weekly man hour cost of company A 7 ten thousand
版权声明
本文为[Fadi]所创,转载请带上原文链接,感谢
https://yzsam.com/2022/04/202204231053145888.html
边栏推荐
- SSH uses private key to connect to server without key
- Full stack cross compilation x86 completion process experience sharing
- Latex usage
- 如何使用JDBC CallableStatement.wasNull()方法调用来查看最后一个OUT参数的值是否为 SQL NULL
- Is the pointer symbol of C language close to variable type or variable name?
- /etc/shadow可以破解吗?
- Swagger2 接口如何导入Postman
- Cve-2019-0708 vulnerability exploitation of secondary vocational network security 2022 national competition
- JDBC – PreparedStatement – 如何设置 Null 值?
- 部署jar包
猜你喜欢

Intuitive understanding entropy

Ueditor -- limitation of 4m size of image upload component

Visualization Road (10) detailed explanation of segmentation canvas function

比深度学习更值得信赖的模型ART

Reading integrity monitoring techniques for vision navigation systems - 3 background

高价买来的课程,公开了!phper资料分享

Visual solutions to common problems (VIII) mathematical formulas

Visual common drawing (I) stacking diagram

Learning note 5 - gradient explosion and gradient disappearance (k-fold cross verification)

SSH uses private key to connect to server without key
随机推荐
第六站神京门户-------手机号码的转换
The courses bought at a high price are open! PHPer data sharing
Typora operation skill description (I) md
SSH利用私钥无密钥连接服务器踩坑实录
How can swagger2 custom parameter annotations not be displayed
Visual common drawing (IV) histogram
最强日期正则表达式
精彩回顾 | DEEPNOVA x Iceberg Meetup Online《基于Iceberg打造实时数据湖》
【leetcode】199.二叉树的右视图
比深度学习更值得信赖的模型ART
454. Sum of four numbers (hash table)
remote: Support for password authentication was removed on August 13, 2021.
Embedded related surface (I)
Linked list intersection (linked list)
Latex usage
24. Exchange the nodes in the linked list (linked list)
VScode
Read integrity monitoring techniques for vision navigation systems
209. Subarray with the smallest length (array)
UDP basic learning