当前位置:网站首页>Mba-day5 Mathematics - application problems - engineering problems
Mba-day5 Mathematics - application problems - engineering problems
2022-04-23 10:55:00 【Fadi】
1. Basic knowledge points
1.1 workload s, The work efficiency v, working hours t The relationship among the three
- workload = The work efficiency * working hours namely s = vt
- working hours = workload / The work efficiency namely t = s/v
- The work efficiency = workload / Time , namely v = s/t
Important note : Time t A certain , Efficiency is directly proportional to the total
1.2 Important conclusions
If Party A completes it alone, it needs m God , Party B needs to complete it alone n God , be
-
- The efficiency of a is 1/m, The efficiency of B is 1/n
-
- The efficiency of cooperation between Party A and Party B is : 1/m + 1/n ( Efficiency can be added or subtracted )
-
- The time required for the completion of the cooperation between Party A and Party B is 1 /(1/m + 1/n)= mn / (m+n)
1.3 Train of thought
Encountered engineering quantity problems , Generally, the whole engineering quantity is ( Water discharge capacity ) See the unit 1, Then solve the problem proportionally according to the problem stem conditions .
It is usually assumed that the total amount ( The amount of work 、 Water discharge capacity )= 1 Analyze
-【 Important formula 】 Total efficiency = Each efficiency algebra and
- The work efficiency = workload / working hours
- Total amount = Partial quantity / Its corresponding proportion
2. Example
- Example 1: Build a highway , Team a's separate construction requires 40 Days to complete , Team B needs to work alone 24 Days to complete , Now both teams are from 2 End start , The result is at the midpoint of the distance 7.5 km Meeting and completion , Then the length of this highway is ()km
Explain : Set the length of this highway s km
Construction by team a alone requires 40 Days to complete , The efficiency of team a is s / 40
Construction by team B alone requires 24 Days to complete , The efficiency of team B is s / 24
From now on, the two teams start from 2 End start , The result is at the midpoint of the distance 7.5 km Meeting and completion
1. From the efficiency, we know that team B is the most efficient
2. A and B are at the midpoint of the distance 7.5 km Meeting and completion , It means that this period of time is the same
3. The construction length of Party A is s/2 - 7.5 km, The construction length of team B is s/2 + 7.5 km
Therefore, the following relationship is obtained : Time = workload / efficiency
(s/2 - 7.5) / (s / 40) = (s/2 + 7.5)/ (s / 24)
(s/2 - 7.5) * (s / 24) = (s / 40) * (s/2 + 7.5)
(s/2 - 7.5) * (1/24) = (1 / 40) *(s/2 + 7.5)
(1/24) / (1 / 40) = (s/2 + 7.5)/ (s/2 - 7.5)
5/3 = (s/2 + 7.5)/ (s/2 - 7.5)
s = 60 km
- Example 2: A project is jointly undertaken by Party A and Party B 30 Days can be done , Team a does it alone 24 Days later , Team B joins , The two teams work together 10 Days later , Team a transferred , Team B continued to do 17 Finish... In days . If the project is done by team a alone , You need to () God
Explain :
According to the workload = working hours * The work efficiency
Let the working efficiency of Party A be x, B. the working efficiency is y, The following relationships can be obtained quickly
30x + 30y = workload
34x + 27y = workload
y = 4/3 x
Bring the above proportion into : nail 30 + B 30 = Quantities completed
30x + 30 * 4/3 x = workload
70x = workload
70 = workload /x = working hours
- Example 3: A unit carries out office decoration , If Party A and Party B cooperate , Need to be 10 Zhou finished . The man hour fee is 100 ten thousand , Company a first does 6 Company B will continue to do it in a week 18 Zhou finished , The man hour fee is 96 ten thousand , Ask company a for the weekly man hour cost ()
Explain , Weekly man hour cost of company A x, Company B's weekly man hour expenses y
If Party A and Party B cooperate , Need to be 10 Zhou finished . The man hour fee is 100 ten thousand , have to 10x+10y = 100
Company a will do it first 6 Company B will continue to do it in a week 18 Zhou finished , The man hour fee is 96 ten thousand , have to 6x+18y=96
10x+10y = 100
6x+18y=96
The most simplified is
x+y =10
x+3y=16
have to y =3, x =7, That is, the weekly man hour cost of company A 7 ten thousand
版权声明
本文为[Fadi]所创,转载请带上原文链接,感谢
https://yzsam.com/2022/04/202204231053145888.html
边栏推荐
- Wonderful review | deepnova x iceberg meetup online "building a real-time data Lake based on iceberg"
- 全栈交叉编译X86完成过程经验分享
- Restful、SOAP、RPC、SOA、微服务之间的区别
- 1. Sum of two numbers (hash table)
- 一个微博数据库设计带来的简单思考
- [Niuke challenge 47] C. conditions (BitSet acceleration Floyd)
- Kaggle - real battle of house price prediction
- remote: Support for password authentication was removed on August 13, 2021.
- 206. Reverse linked list (linked list)
- Visual common drawing (I) stacking diagram
猜你喜欢

Solutions to common problems in visualization (IX) background color

/etc/shadow可以破解吗?

【leetcode】102. Sequence traversal of binary tree

《Neo4j权威指南》简介,求伯君、周鸿袆、胡晓峰、周涛等大咖隆重推荐

精彩回顾 | DEEPNOVA x Iceberg Meetup Online《基于Iceberg打造实时数据湖》

Solution architect's small bag - 5 types of architecture diagrams

VIM + ctags + cscope development environment construction guide

Google Earth Engine(GEE)——将原始影像进行升尺度计算(以海南市为例)

使用zerotier让异地设备组局域网

使用 PHP PDO ODBC 示例的 Microsoft Access 数据库
随机推荐
Visualized common drawing (II) line chart
Visual solutions to common problems (VIII) mathematical formulas
Reading integrity monitoring techniques for vision navigation systems - 3 background
Hikvision face to face summary
【leetcode】102. Sequence traversal of binary tree
How can swagger2 custom parameter annotations not be displayed
mysql同一个表中相同数据怎么合并
JVM - common parameters
Visual common drawing (III) area map
707. Design linked list (linked list)
Typora operation skill description (I) md
比深度学习更值得信赖的模型ART
解决方案架构师的小锦囊 - 架构图的 5 种类型
How to Ping Baidu development board
使用zerotier让异地设备组局域网
Reading integrity monitoring techniques for vision navigation systems - 5 Results
Charles function introduction and use tutorial
Swagger2 接口如何导入Postman
/Can etc / shadow be cracked?
The difference between restful and soap